Scottish Court of Session Decisions
You are here:
BAILII >>
Databases >>
Scottish Court of Session Decisions >>
THE COAL AUTHORITY AGAINST PEGASUS FIRE PROTECTION COMPANY LIMITED [2018] ScotCS CSOH_36 (12 April 2018)
URL: http://www.bailii.org/scot/cases/ScotCS/2018/[2018]_CSOH_36.html
Cite as:
[2018] ScotCS CSOH_36,
[2018] CSOH 36
[
New search]
[
Printable PDF version]
[
Help]
Page 1 ⇓
OUTER HOUSE, COURT OF SESSION
[2018] CSOH 36
CA87/17
OPINION OF LORD BANNATYNE
In the cause
THE COAL AUTHORITY
against
PEGASUS FIRE PROTECTION COMPANY LIMITED
Pursuer
Defender
12 April 2018
Pursuer: Lindsay QC; DLA Piper Scotland LLP
Defender: MacColl QC; Davidson Chalmers LLP
Introduction
[1] This matter came before me as a debate in the commercial court at the instance of the
defender.
[2] The issue for determination by the court was: whether or not the defender is obliged
to indemnify the pursuer, under and in terms of condition 12 of the pursuer’s terms and
conditions, in respect of all costs incurred by the pursuer in carrying out remedial action in
respect of subsidence damage at the site (where the defender carried out work) in
performance of its statutory duties under section 2 of the Coal Mining Subsidence Act 1991?
Page 2 ⇓
2
Background
[3] The parties’ respective positions as set out in their pleadings are, in short, these:
[4] The pursuer avers that the defender is liable to indemnify it because the defender
carried out its work at the site under and in terms of the December 2010 permission,
April 2011 permission and the extension; all of which were subject to the pursuer’s terms
and conditions.
[5] These terms and conditions included condition 12 which imposed an obligation
upon the defender to indemnify the pursuer for a period of 12 years against liability for
claims, losses or damages arising as a result of any failure by the defender to comply with
the requirements of the permissions or as a result of any act, failure, inadequacy, omission,
negligence or default by the defender in designing or carrying out the work.
[6] The pursuer avers that the cost it has incurred under section 2 of the 1991 Act were
caused by the defender’s failure to identify a mine-related risk to structures at the site and
therefore these costs fall within the scope of the indemnity created by condition 12.
[7] The defender denies any liability to indemnify the pursuer because it avers that the
extension, which related to the treatment works relied upon by the pursuer in its pleadings,
was not a retrospective extension of the April 2011 permission as averred by the pursuer and
therefore the treatment works are not subject to the pursuer’s terms and conditions.
[8] The defender further avers that the indemnity granted by the defender to the
pursuer extended only to the works covered by the December 2010 permission and the
April 2011 permission.
[9] The defender’s position in short is that the pursuer’s primary case as averred is
irrelevant.
Page 3 ⇓
3
[10] The pursuer also avers an alternative case that it is entitled to an indemnity based on
the defender’s “unauthorised failure to comply with the terms of the April 2011
permission”. The defender’s position is that this case is also irrelevant.
Submissions on behalf of the defender
[11] The defender’s argument at debate was this: the action is irrelevant on three
grounds:
The pursuer predicates its primary case against the defender, in short, on the
basis that certain documents founded upon by it, and, in particular, the email
from Leigh Sharpe of 25 May 2012, gives rise to an obligation of indemnity on
the part of the defender. The email of 25 May 2012, however, does not fall to
be construed as giving rise to any indemnity on the part of the defender.
The pursuer’s alternative claim is that it is entitled to indemnity from the
defender as a result of a breach of the permission of April 2011. This case is
also irrelevant.
Finally, the pursuer gives no proper notice of the demolition and remedial
works which it suggests may be required, or, flowing from this, the reasons
why they are required or their cost. The pursuer’s case is accordingly lacking
in specification in that regard.
[12] Turning to his first argument Mr MacColl submitted that the background to the
25 May email was of some importance. The material averments regarding the background
to the email were these:
“In application made by the Defender to the Pursuer dated 7 December 2010, the
Defender sought permission to enter or disturb the Pursuer’s mining interests
through investigation of shallow mine workings at the Site. A map of the Site
Page 4 ⇓
4
provided by Fife Council as an attachment to its e-mail correspondence dated
9 February 2016 is produced.
By way of a permit issued by the Pursuer dated 9 December 2010 (hereinafter
referred to as the ‘December 2010 Permission’) the Pursuer granted to the Defender
permission to enter or disturb the Pursuer’s mining interests by carrying out works
described as ‘Investigation of Shallow Mine Workings, 3 boreholes’ within the Pursuer’s
mining interests at the Site. The December 2010 permission was issued by the
Pursuer to the Defender, by way of correspondence dated 9 December 2010 and was
in force for a period of 12 months from 9 December 2010. Copies of the
December 2010 Permission and the application forms for the December 2010
Permission dated 1 and 7 December 2010 are produced.
April 2011 Permission
On 11 April 2011 (hereinafter referred to as the ‘April 2011 Permission’), the Pursuer
agreed with the Defender’s engineering contractor, LK Consult Limited, to
retrospectively extend the December 2010 Permission. The April 2011 Permission
granted the Defender retrospective permission to carry out works described as
‘Investigation of Shall Mine Workings by 16 additional boreholes’ within the Pursuer’s
mining interests at the Site for a period of 12 months from 11 April 2011. A copy of
the April 2011 Permission is produced.” (see: article 4 of condescendence at pages 8
and 9).
[13] The application for the December 2010 Permission was pursuer’s production number
5/1 of process, the December 2010 Permission was pursuer’s production number 5/2 of
process and carried a Permit Reference Number 5728, the April 2011 Permission was
pursuer’s production number 5/3 of process and carried a Permit Reference Number 5728.1.
[14] Mr MacColl observed that the application, no 5/1 of process, was made formally on
behalf of the defender. The application was made on the basis that the defender accepted
certain conditions set out in the application form. Condition 12, the indemnity obligation,
was one of the conditions set out in the form. Thereafter a formal permission was granted
(no 5/2 of process).
[15] In respect to the April 2011 Permission again there was a formal permission which
granted “retrospective permission to carry out the investigation of shallow mine workings
by 16 additional boreholes …”
Page 5 ⇓
5
[16] In particular he noted that the April 2011 permission was not a retrospective
extension of another permission.
[17] Against that background he turned to look at the meat of the pursuer’s primary case
which was contained at page 9 of the closed record and was in the following terms:
“On 25 May 2012 the Pursuer agreed to retrospectively extend the April 2011
Permission to cover the treatment works that had been carried out at the Site
(hereinafter referred to as the ‘Extension’). A copy of the e-mail correspondence
relative to the Extension dated 25 May 2012 is produced. The e-mail’s confirmation
that Permit 5728 could ‘now be closed out’ and that the permit file had been
‘updated’ to reflect the ‘closure and receipt of all particulars’ received from the
defender makes clear that the April 2011 Permission was retrospectively extended to
cover the treatment works that had been carried out at the Site.”
[18] The said email’s whole terms are these:
“Thank you for providing us both with the SI report and the treatment completion report for
the stabilisation works at Townsend Place. I can confirm that we are satisfied with the
information provided such that the Permit (our ref. 5728) can now be closed out. The
information you provided will be passed to our surveyors so that the database can reflect the
treatment undertaken. The permit file has now been updated to reflect the closure and receipt
of all particulars from yourselves.
We thank you for your patience in awaiting our response. If you have any questions please
don’t hesitate in contacting me.”
[19] The first point Mr MacColl made in respect to this passage of the pleadings was this:
the April 2011 Permission which the pursuer contended was “retrospectively extended” had
a reference number 5728.1. There is no reference to that permission in the email, rather what
is referred to is “Permit 5728”, the December 2010 Permission. The April 2011 Permission
makes no reference to permit 5728 and does not say that it is a retrospective permission to
extend permission 5728.
[20] Moreover, the email of 25 May cannot be read as a retrospective extension of the
permission of 11 April 2011. It is no more than an email noting that an SI report and
treatment completion report has been provided to the pursuer by Groundshire Ltd; that the
pursuer is satisfied by the information provided by Groundshire Ltd; and that the pursuer’s
Page 6 ⇓
6
permit 5728 is now closed. It does not state that any extension of any existing permit or
permission is being granted or, that any new permission is being granted. It is not a permit
from the pursuer, examples of which are 5/2 and 5/3 of process.
[21] Beyond that, the email, which was sent on behalf of the pursuer to Groundshire, is
not and cannot be read as the grant or extension of a contractual indemnity by the defender
in respect of works that have taken place in the period up to 25 May 2012.
[22] In expansion of that position he said this: the contractual indemnity which had been
granted by the defender to the pursuer extended only to the works covered by the
permission of 9 December 2010 (“investigation of shallow mine workings, 3 boreholes”) and
the permission of 11 April 2011 (“investigation of shallow mine workings by 16 additional
boreholes”). It did not extend to the wider matters upon which the pursuer now advanced
its action. He submitted that there is nothing produced by the pursuer that would amount
to any bargain between the pursuer and defender that the indemnity which the defender
previously agreed to provide should be extended to cover treatment works, in respect of
which no permit had ever been issued by the pursuer.
[23] Mr MacColl then moved on to make certain submissions regarding background
materials which were founded upon by the pursuer as being materials, which if read with
the email of 25 May, gave it the meaning contended for on behalf of the pursuer.
[24] His position regarding these various documents was this: there is nothing in the
background materials leading up to the email of 25 May which suggests that the email of
25 May 2012 should be read as imposing a binding indemnity obligation upon the defender
in respect of the “treatment works”. The pursuer founds upon the following: (a) the
application of 1 and 7 December 2010; (b) the permit of 9 December 2010; (c) the permit of
11 April 2011; (d) an email dated 16 January 2012 from Groundshire; and (e) the email of
Page 7 ⇓
7
25 May 2012. The first three of these documents he submitted show that the pursuer has a
formal process with an applicant formally signing up to an indemnity obligation and being
granted a formal permit for works. This, he argued, plainly does not assist the pursuer in its
attempt to assert that a later email, which had no accompanying formal permit, should be
regarded as somehow imposing an extended indemnity obligation. The email of
16 January 2012 is also of no assistance to the pursuer.
[25] In the email of 16 January 2012, Groundshire writes to the pursuer stating:
“Further to our recent telephone conversation (about which the pursuer makes no
averments), I have sent our two completion reports, for the exploratory drilling and
the treatment works, on CD by post. Please find attached a copy of Raeburn’s
borehole logs and location plan. Could you send me an email confirming that the
extension covers the treatment work as well.”
[26] He then observed that no email is produced or founded upon by the pursuer stating
that the extension covers the treatment works.
[27] He then turned to deal with certain averments which were made in terms of a
minute of amendment which was allowed to be received and in terms of which the
pleadings were amended on the morning of the debate. In terms of that minute of
amendment the pursuer sought to found upon a further email from the pursuer dated
16 January 2012. Mr MacColl’s position regarding this was: it does not assist the pursuer. It
states: “… When I receive the disks we’ll review and issue a permit to cover the treatment,
this may be referred to as 5728.2”. Thus he submitted, it is plain that any extension of the
prior permit would be by way of a further formal permit. No such document has been
produced by the pursuer. Indeed, the pursuer does not offer to prove that any such
document exists.
Page 8 ⇓
8
[28] All that happens following the said email of 16 January 2012, is that some four
months later, the email of 25 May is sent. There is no reference in that email to
permission 5728.2 which is referred to in the email of 16 January 2012.
[29] Mr MacColl concluded his submissions by noting that the correspondence upon
which the defender relied was all with Groundshire. There was nothing in the averments
that Groundshire was the agent of the defender in respect to the matter of the grant or
extension of a contractual indemnity by the defender. There are not even any averments
that the defender was aware of the content of this correspondence.
[30] The pursuer is required to show that the defender agreed to a contractual obligation
which imposes upon it an obligation of indemnity in respect of the treatment works. In
these circumstances there were no averments which could impose such an obligation on the
defender.
[31] For these reasons the pursuer’s principal case is irrelevant.
[32] The pursuer also advanced a secondary alternative case in terms of which it is
contended that the defender has failed to comply with the permission of April 2011.
[33] The core of the pursuer’s alternative case is in article 4, page 10 of the closed record:
“Esto the April 2011 Permission was not retrospectively extended to cover the
treatment works that had been carried out at the Site for the reasons averred by the
defender (which is denied), the treatment works were an unauthorised failure to
comply with the terms of the April 2011 Permission.”
[34] Mr MacColl’s response to this alternative case was a short one: the foundation of this
alternative case is a non sequitur.
[35] He argued that the carrying out of treatment works, the activity identified by the
pursuer in its pleadings at article 4, does not amount to a failure to comply with the
April 2011 permission. Notably, the pursuer does not offer to prove that the defender did
Page 9 ⇓
9
not carry out the “investigation of shallow mine workings by 16 additional boreholes”
which is the permitted activity under the April 2011 permission.
[36] For this reason, the pursuer’s alternative case is also irrelevant.
[37] The pursuer’s third argument was a short one of specification. Mr MacColl
submitted there was no proper notice of the demolition and remedial works, which the
pursuer suggests may be required. He submitted that in order for proper advice to be given
to the defender, there needed to be a basis averred for the pursuer’s valuation of the claim
together with a valuation of that claim.
[38] The defender’s specification argument only came into play if the court were against it
in respect of the relevancy argument. Mr MacColl accepted that it would not be appropriate
to dismiss the pursuer’s action in terms of this argument. Rather, what he sought was an
order from the court that the pursuer should provide further specification of its position.
The reply on behalf of the pursuer
[39] Mr Lindsay’s position in summary regarding the first argument advanced by
Mr MacColl was this: the pursuer’s averments that the email of 25 May 2012 is a
retrospective extension of the permission of 11 April 2011 are relevant and a proof before
answer should be allowed in respect of them.
[40] Mr Lindsay began by saying that it was important to understand that what was not
being dealt with in this case was a statutory scheme for indemnity. The issues before the
court were matters of contract. The pursuer was not required to grant permission in a
particular form. What was important in considering the issues before the court was
substance not form.
Page 10 ⇓
10
[41] He described the defender’s position as being wholly lacking in merit. The email of
25 May 2011 clearly extended the April 2011 permission to cover the treatment works that
had been carried out at the site.
[42] In elaboration of this position he submitted: the email confirms that permit 5728
could “now be closed out” and that the permit file had been “updated” to reflect the
“closure and receipt of all particulars” received from Groundshire, on behalf of the
defender. The foregoing makes clear that the April 2011 permission was retrospectively
extended to cover the treatment works that had been carried out at the site. There is no
other reasonable interpretation which can be placed upon these expressions. In its
pleadings, in its note of argument and in the oral submissions advanced, the defender had
not provided any alternative interpretation of these key expressions.
[43] Mr Lindsay then turned to the context in which the email of 25 May 2012 was sent. It
was his position that this context was of some importance in relation to the issue of
construction. It was sent in response to the submission of an SI report and a treatment
report for the stabilisation works by Groundshire on behalf of the defender. These reports
made clear that additional works, which were not covered by the April 2011 permission, had
been carried out. These additional unauthorised works were the treatment works which
form the subject matter of the present action. He submitted this: the sole purpose of
submitting these reports was to obtain retrospective authorisation of the treatment works.
There was no other purpose or reason for submitting them to the pursuer at that stage of the
development.
[44] Again Mr Lindsay stressed that in its pleadings, note of argument and oral
submissions, the defender had not averred any alternative explanation for the submission of
those reports. The defender’s failure to do so he submitted is significant and highlights that,
Page 11 ⇓
11
in reality, there is no real dispute that the foregoing is why the reports were submitted to the
pursuer.
[45] In addition, the email of 28 May 2012 from Ellen Dempster, in reply to the email of
25 May 2012, demonstrates that there was a consensus between Groundshire, on behalf of
the defender, and the pursuer that the April 2011 permission had been retrospectively
extended to cover the treatment works. The email of 28 May 2012 thanks the pursuer and
does not seek any clarification of what had been granted by the pursuer. There was no need
to do so as both parties understood that the April 2011 permission had been retrospectively
extended.
[46] In answer to the argument advanced by Mr MacColl that none of this
correspondence could bind the defender in respect to an indemnity in respect of the
treatment works he made a number of points:
The defender signed the standard terms and conditions of the pursuer, when
it made its initial application.
The defender therefore knew and accepted the above conditions.
He directed the court’s attention to the numbering on the two permissions
granted, namely: 5728 and 5728.1. The reference in the email of
16 January 2012 to permit 5728.2.
This evidenced that what was happening was all part of one process.
5728.1 was applied for by a contractor of the defender, namely: LK Consult
Ltd and no issue was taken by the defender in respect to that retrospective
extension. The defender was not saying that there was any difficulty with the
permission of April 2011.
Page 12 ⇓
12
Thereafter it was averred on behalf of the pursuer that a second extension
was sought by another of the defender’s contractors.
The above showed a pattern of behaviour, namely: extensions sought by
various contractors of the defender and granted by the pursuer.
The above, when taken together was enough to show Groundshire was the
defender’s agent. Accordingly the defender was bound by the indemnity in
respect to the treatment works. It was thereafter for the defender to say that
it was not bound by Groundshire. The defender made no such averment.
[47] It was Mr Lindsay’s position that the issue between the parties was a matter for proof
before answer. When the chain of emails was read he submitted that it was clear that
Groundshire recognised that there was a problem in respect to the issue of permission
regarding the “treatment works”. This required to be sorted out and that was done by the
email of 25 May. What had happened by the email of 25 May was that a second extension
had been granted.
[48] He further said this in respect to allowing a proof before answer: Mr Sharpe will
come along and explain the email 25 May and what it was intended to mean.
[49] Turning to the alternative case advanced by the pursuer it was Mr Lindsay’s position
that this was shown to be relevant by regard being had to the terms of condition 12 of the
pursuer’s terms and conditions and to the nature of the treatment works which were carried
out.
[50] Condition 12 of the pursuer’s terms and conditions provides:
“The applicant shall, for a period of 12 years from the date of completion of the
works, indemnify the Authority against liability for claims, losses or damages,
including those made under the Coal Mining Subsidence Act 1991 and claims by the
Applicant, whether arising as a result of any failure by the Applicant or the
Applicant’s contractors, to comply with the requirements of this permission or as a
Page 13 ⇓
13
result of any act, failure, inadequacy, omission, negligence or default by the
Applicant or the Applicant’s contractors in designing or carrying out the work.”
[51] The April 2011 Permission merely permitted the defender to carry out an
investigation of shallow mine workings by 16 additional boreholes within the pursuer’s
mining interest. The April 2011 Permission did not authorise or otherwise permit the
defender to carry out the treatment works.
[52] The carrying out of the treatment works was a failure by the defender to comply
with the requirements of the April 2011 Permission and therefore the defender is obliged by
condition 12 to indemnify the pursuers against liability for all claims, losses or damages
arising as a result of this failure.
[53] Accordingly regardless of whether or not the April 2011 permission was validly
retrospectively extended to cover the treatment works, the defender is required to
indemnify the pursuer under and in terms of condition 12.
[54] On the third specification issue he briefly submitted that there is no merit in the
submission that there is a lack of specification. The pursuer has provided adequate
specification of the anticipated demolition and remedial costs in the context of an action
which merely seeks declarator rather than an order for payment of a particular sum.
[55] In article 23 of condescendence the pursuer avers the remedial costs would amount
to £1,090,000 and that it has already incurred costs of £21,500 in relation to site
investigations, valuation fees and maintenance costs. In addition, a letter dated
26 September 2016 from the pursuer is incorporated brevitatis causa into the pursuer’s
pleadings. This letter provides a detailed breakdown of the estimated remedial costs.
[56] He submitted that these averments provided sufficient specification to enable the
defender to ascertain the likely extent of its indemnity obligations and whether it is
necessary and cost effective to defend this action.
Page 14 ⇓
14
Discussion
The primary relevancy argument
[57] I am persuaded that the email of 25 May 2012 does not on a sound construction have
the meaning contended for by the pursuer.
[58] The pursuer maintains that on a sound construction it amounts to the pursuer
agreeing to “retrospectively extend the April 2011 Permission to cover the treatment works”.
[59] Nowhere in that email is there any reference to the April 2011 permission. The
Permit Reference Number of that permission is 5728.1. The only reference in the email to a
permit is to 5728 (the December 2010 permission).
[60] 5728.1 is a separate permission from 5728. It grants “retrospective permission to
carry out the investigation of shallow mine workings by 16 additional boreholes”. I observe
that in particular it does not retrospectively extend the December 2011 Permission. On a
sound construction it is an entirely separate permission from 5728.
[61] Moreover, I believe that Mr MacColl is correct in characterising the email of 25 May
in this way: as an email which merely notes that an SI report and treatment completion
report has been provided to the pursuer by Groundshire Ltd and that the pursuer is satisfied
by information provided by Groundshire Ltd and that the pursuer’s permit 5728 is now
closed.
[62] On the ordinary and natural meaning of the words used in the email of 25 May no
extension of any existing permit or permission is granted. It does not state that any
extension of any existing permit is being granted.
[63] The pursuer’s case is not assisted by reference to context. All of the arguments
advanced by Mr MacColl in relation to this matter in my view have considerable force.
Page 15 ⇓
15
[64] In particular it seems to me that the terms of the email added by minute of
amendment tend to show that the pursuer’s construction is not correct. I agree with
Mr MacColl that on a true construction of that document any extension was to be by way of
the issuing of a formal permit “5278.2”, as happened in respect to the earlier original
application, no 5/2 of process, and in respect of the April 2011 retrospective extension, no 5/3
of process. On the pursuer’s averments no such document has been issued. I observe that in
addition, in the 25 May 2012 email, there is no reference to a permit with a reference
number 5278.2
[65] Moreover, there is nothing in the email of 25 May 2012 when taken together with the
other correspondence founded upon by the pursuer which could amount to an agreement
between the pursuer and defender that the indemnity which the defender had previously
agreed to provide should be extended to cover the treatment works where no permit relative
to those works has been issued by the pursuer.
[66] Further, it is noteworthy that the email of 25 May 2012 which is principally founded
upon by the defender is to Groundshire. The other emails which are founded upon by the
pursuer are also to or from Groundshire. Such correspondence cannot be read as the grant
or an extension of a contractual indemnity by the defender to cover the treatment works.
There is no correspondence with the defender founded upon by the pursuer. The defender
is not copied in with respect to any of the emails founded upon. There is nothing in this
correspondence, or in the background thereto, from which it could be argued that
Groundshire was acting as agent for the defender in respect to a contractual obligation
which imposes upon the defender an obligation to indemnify in respect of the treatment
works.
Page 16 ⇓
16
[67] It does not follow as asserted by Mr Lindsay that because Groundshire was a
contractor working on the site for the defender that it was an agent for the defender in
respect of a grant or extension of a contractual indemnity. I believe this argument is clearly
wrong in law. The employing of a contractor, of itself, does not authorise them to act as
agents for the employer in relation to third parties.
[68] Mr Lindsay argued that it was for the defender to aver that Groundshire was not its
agent. I do not believe that is correct. It is for the pursuer to aver that Groundshire was
acting as an agent for the defender and to aver the basis for that assertion. It does not do so.
[69] Mr Lindsay sought to rely on a number of factors when taken tougher in order to
show that Groundshire was the defender’s agent in relation to the granting or extension of
the indemnity.
[70] To begin with he relied on the defender signing the original application. It therefore
had knowledge of the terms and in particular the terms of the indemnity and accepted these.
That is of course correct but it does not seem to me to take the pursuer anywhere. That
knowledge relates only to the granting of permissions 5728 and 5728.1. That the defender is
bound by the conditions including the obligation of indemnity in relation to these
permissions is not a matter of dispute.
[71] He sought to argue that permission 5728 and 5728.1 and the further extension
granted in respect to the treatments works were connected. They were all part of one
process. I do not believe that is correct for the reason which I have earlier given, namely:
5728.1 is not an extension of 5728. It makes no reference to permission 5728. It appears to be
an entirely separate permission from 5728. I am not persuaded this is a single process. If it
was why are 5728.1 and the extension, which the pursuer maintains is granted relative to the
treatment works not said to be extensions of permission 5728.
Page 17 ⇓
17
[72] He then argued that 5728.1 was granted on the basis of an application by other
contractors of the defender and the defender was not saying that there was any difficulty
with that permission. I do not think that this takes the pursuer anywhere. It does not follow
because that permission has not been challenged that the defender is not entitled to argue
that no permission was granted for the treatment works and that the defender’s indemnity
was not extended to cover the treatment works. It is also noteworthy that the two
contractors are not the same and that the LK group is referred to in the defender’s original
application as their consultants and there is no reference to Groundshire in the original
application. Mr Lindsay then reminded the court of the email correspondence between the
pursuer and Groundshire another contractor of the defender resulting in the email of
25 May.
[73] He then argued that having regard to all of the foregoing a pattern of extensions
being applied for by contractors of the defender and being granted emerged. From this it
was clear that Groundshire was acting as an agent for the defender.
[74] There is nothing in these factors individually or when taken together which points to
a relationship of agency between the defender and Groundshire in respect to the granting or
extending of an indemnity by the defender to cover the treatment works. The factors
individually amount to nothing and when taken together do not lead to the conclusion
contended for by the pursuer. No pattern of the type relied on by the pursuer emerges.
What is referred to is a number of separate and individual events.
[75] In conclusion I agree with Mr MacColl that there is nothing produced by the pursuer
that would amount to an agreement between it and the defender that the indemnity which,
the defender accepts, it previously agreed to provide should be extended to cover the
Page 18 ⇓
18
treatment works in respect of which no permit has ever been issued by the pursuer. The
pursuer’s primary case is accordingly irrelevant.
[76] There is one further matter in respect to his primary argument upon which I would
wish to comment. Mr Lindsay in the course of his submission said that all of the issues were
properly a matter for proof before answer. He said this “Mr Sharpe (the author of the email
of 25 May relied on by the pursuer) will come along and explain what the email of 25 May
was intended to be” if such evidence were to be allowed, it would not advance the pursuer’s
case. It appeared to me that Mr Lindsay was seeking to put forward evidence of the
intention of Mr Sharpe in saying what he did in the email of 25 May. That is not a relevant
consideration in arriving at a true construction of the document.
[77] In respect to the pursuer’s alternative case I believe it is misconceived.
[78] The pursuer’s substantive case against the defender is that the treatment works were
not carried out properly and caused damage through subsidence at the site.
[79] The April 2011 Permission is a permission: “to carry out investigation by
16 additional boreholes”. It is not a permission to carry out “treatment works”. The
pursuer’s substantive case is not that the pursuer has a statutory obligation to make
payment which the defender is obliged to indemnify because the work in respect of the
16 boreholes was not carried out, but that the treatment works were not properly carried
out.
[80] This leads to the non sequitur in the pursuer’s pleadings about which Mr MacColl
complains, namely: the averment that there has been a failure to comply with the terms of
the April 2011 Permission. Mr MacColl is correct in arguing that the carrying out of
treatment works does not amount to a failure to comply with the April 2011 Permission.
Page 19 ⇓
19
[81] There is nothing in the pleadings of the pursuer explaining why the treatment works
should in any way be held to be related to the 2011 permission. I agree with Mr MacColl
that in considering this point it is notable that the pursuer does not offer to prove that the
defender failed to carry out the work identified in the April 2011 permission. This is an
adminicle pointing away from the April 2011 permission having anything to do with the
case as pled by the pursuer against the defender. The pursuer does not offer to prove that
anything done in terms of the April 2011 permission gave rise to the problems upon which it
bases its case.
[82] Mr Lindsay directed the court’s attention to condition 12 and said that the part of the
indemnity relied upon in respect to the alternative argument was: “the failure to comply
with the requirements of this permission”.
[83] On a sound construction, what the foregoing does not mean is this: if you carry out
works beyond what is permitted in terms of the April 2011 Permission that engages the
indemnity provision. There is nothing before the court to the effect that carrying out
treatment works breached the contract between the parties.
[84] What, properly understood, is the pursuer’s complaint as advanced in its alternative
case? I believe the complaint is one of trespass in respect to the pursuer’s mining interest
and that it is seeking to recover damages arising from trespass. That however, does not
engage the contractual indemnity.
Decision
[85] For the foregoing reasons I consider that both the pursuer’s primary and alternative
cases are irrelevant.
Page 20 ⇓
20
Disposal
[86] In light of the above I sustain the defender’s first and fourth pleas in law and dismiss
the action.
The specification issue
[87] Had I required to deal with the specification issue I would have held that sufficient
specification was provided, for the reasons advanced by Mr Lindsay.